Action Title |
Location |
Institution in charge |
Operation and Remarks |
|
1.For under construction projects priority will be given to the completion of main canal construction works. |
|
Adıyaman-Çamgazi Irrigation |
Adıyaman |
DSİ |
In Çamgazi irrigation construction will be completed in the remaining area of 3,811 hectares. |
|
Samsat pumped irrigation . Part I |
Adıyaman |
DSİ |
In Samsat pumped irrigation . Part I, construction will be completed in the remaining area of 2,246 hectares. |
|
Batman Stage II |
Batman |
DSİ |
Main canal constructions for Batman right and left bank irrigations (292 km in total) will be completed. |
|
Kralkızı-Dicle . Stage I |
Diyarbakır |
DSİ |
In Kralkızı-Dicle gravity and pumped irrigations Part I, main canal (60 km) and network (17,729 hectares) constructions will be completed. |
|
Lower Euphrates . Stage I |
Şanlıurfa |
DSİ |
Upper Harran main canal will be completed up to 86th km. In Upper Harran Plain irrigation (2,888 hectares) and Harran Plain irrigation 6th Part (7,974 hectares) related constructions will be completed. |
|
Kayacık |
Gaziantep |
DSİ |
Kayacık Plain irrigation main canal (34 km.) construction works will be completed. |
|
Belkıs-Nizip Irrigation |
Gaziantep |
DSİ |
Belkıs-Nizip (43 km) irrigation network main canal construction works will be completed. |
|
2. Cooperation will be sought in the construction of irrigation networks for priority projects (i.e. water source is already available). |
|
Batman Stage II |
Batman |
DSİ |
Batman right bank (18,193 hectares) and left bank (17,903 hectares) irrigation networks will be completed. |
|
Kralkızı-Dicle I. and Stage II |
Diyarbakır |
DSİ |
Construction of Kralkızı-Dicle I. and Stage II irrigation networks (97,893 hectares) will be given start and large part of contractions will be completed at the end of the period. |
|
Suruç Plain Pumped Irrigation Stage I |
Şanlıurfa |
DSİ |
Suruç Stage I irrigation network (57,927 hectares) will be given start and most of the construction will be completed until the end of the period. |
|
Bozova Pumped Irrigation l, construction of II. and III. Parts |
Şanlıurfa |
DSİ |
Construction of I. and II. Parts of Bozova Pumped Irrigation Facilities (36,819 hectares) will be completed. |
|
Kayacık |
Gaziantep |
DSİ |
Kayacık Plain (18.800 hectares) irrigation network will be completed. |
|
Belkıs-Nizip Irrigation |
Gaziantep |
DSİ |
Belkıs-Nizip (11.925 hectares) irrigation network will be completed. |
|
Koçali Dam Irrigation |
Adıyaman |
DSİ |
In Koçali Dam (Adıyaman) irrigation network (21.605 hectares) will be completed. |
|
Mardin-Ceylanpınar and Mardin Water Storage Irrigations |
Mardin |
DSİ |
Mardin-Ceylanpınar (67,106 hectares) and Mardin Gravity Storage (27,883 hectares) networks will be given start and most of the construction will be completed until the end of the period. |
|
Mardin Ceylanpınar YAS Sulaması |
Mardin |
DSİ |
Mardin Ceylanpınar Underground (YAS) (111.939) irrigation networks will be given start and most of the construction will be completed until the end of the period. |
|
3. In priority (i.e. water source is already available) projects main canal construction works will be started and largely completed at the end of the term. |
|
Kralkızı-Dicle 1. and Stage II |
Diyarbakır |
DSİ |
To serve an area of 97,893 hectares, 202 km long Kralkızı-Dicle I. and Stage II Projects main canal construction works will be completed. |
|
Suruç Plain Pumped Irrigation Stage I |
Şanlıurfa |
DSİ |
In Suruç Stage I project which is to serve an area of 57,927 hectares, construction of 160 km long main canal will be completed. |
|
Mardin-Ceylanpınar and Mardin Water Storage Irrigations |
Mardin |
DSİ |
To serve an area of 94,929 hectares, construction of 136 km long Mardin-Ceylanpınar main canal will be completed. main canal construction will be completed. |
|
4. In projects without storing facility, priority will be given to dam and main canal construction. |
|
Batman Silvan Project |
Diyarbakır |
DSİ |
To serve an area of 193,249 hectares, construction of Silvan Dam main storage facilities and main canal (63 km) will be given start in the programme period and most of it will be completed in the same period. |
|
Adıyaman Göksu Araban Project |
Adıyaman |
DSİ |
To serve an area of 71,598 hectares, construction of Çetintepe main storage, intermediary storages and main canal will be given start in the programme period and most of it will be completed in the same period. |
|
5. Expropriations will take place in ongoing constructions and others to be launched in the programme period. |
|
Batman Stage II |
Batman |
DSİ |
|
|
Kralkızı-Dicle 1. and Stage II |
Diyarbakır |
DSİ |
|
|
Suruç Plain Pumped Irrigation Stage I |
Şanlıurfa |
DSİ |
|
|
Bozova Pumped Irrigation construction of II. and III. Parts |
Şanlıurfa |
DSİ |
|
|
Kayacık |
Gaziantep |
DSİ |
|
|
Belkıs-Nizip Irrigation |
Gaziantep |
DSİ |
|
|
Koçali Dam Irrigation |
Adıyaman |
DSİ |
|
|
Mardin-Ceylanpınar and Mardin Water Storage Irrigations |
Mardin, Şanlıurfa |
DSİ |
|
|
Mardin Ceylanpmar Underground Irrigation (YAS) |
Mardin |
DSİ |
|
|
Batman Silvan Project |
Diyarbakır |
DSİ |
|
|
Adıyaman-Kahta (Samsat Pumped irrigation) |
Adıyaman |
DSİ |
|
|
Adıyaman-Çamgazi |
Adıyaman |
DSİ |
|
|
6. In-farm drainage works will be completed in ongoing projects. |
|
Lower Euphrates Stage I on-farm drainage |
Şanlıurfa |
DSİ |
|
|
Yaylak Plain Irrigation on-farm drainage |
Şanlıurfa |
DSİ |
|
|
Bozova Pumped Irrigation on-farm drainage |
Şanlıurfa |
DSİ |
|